Permit Required? Depends on scope (finishes exempt)
Typical Fee Range $740–$1,850 Cabinets, counters, tile and paint are exempt; fixtures, circuits, gas and walls are not
Fee Method $211 processing + tiered inspection fee + plan check

What's Required in San Jose

  • Painting, tiling, cabinets, counter tops and similar finish work need no building permit (SJMC 24.02.120.A.9)
  • Replacing or relocating fixtures, or replacing a defective concealed pipe, needs a plumbing permit (SJMC 24.02.130)
  • New circuits, receptacles, lighting and appliances need an electrical permit; same-location breaker, switch or receptacle replacement is exempt (SJMC 24.02.150)
  • Range hood or exhaust fan and gas line work need mechanical permits; gas rough and final need both mechanical and plumbing permits
  • Opening, removing or moving a wall is a Kitchen Major structural alteration with plans (SJMC 24.02.220)
  • Work is reviewed under the 2025 California codes in effect since January 1, 2026
  • Rough plumbing, mechanical, gas and electrical inspected before concealment; final inspection at completion
  • Owner-builders may pull permits; contractors need a state license for jobs of $1,000 or more
  • Permits expire after 12 months without a start or 180 days without progress; extensions $105

Do You Need a Permit to Remodel a Kitchen in San Jose?

It depends on what is behind the finishes. San Jose Municipal Code 24.02.120 exempts painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work from a building permit, so a new-look kitchen in the same layout with the same sink, range and circuits needs nothing from the city. The permit starts the moment you touch a system: the plumbing exemption covers only stopping leaks and clearing stoppages, and replacing a defective concealed drain or supply line is expressly new work needing a permit; the electrical exemption reaches only minor repairs, lamp changes and a same-location breaker swap. New circuits, a relocated sink, a gas line to a new range position, a moved wall or a pass-through are all permitted work, and SJPermits.org lists the pieces it can issue online: fixture replacements, receptacles and switches, light fixtures, appliances, gas line rough and final, and drain-waste-vent or water alterations.

San Jose Kitchen Remodel Rules by Scenario

What you are doingCity filingRule
New cabinets, countertops, backsplash, flooring, paint; same layoutNo permitSJMC 24.02.120.A.9
Replacing the sink, faucet, dishwasher or disposal in the same spotOnline plumbing permit (Fixture Single Replacement or Appliance)SJPermits online permits; SJMC 24.02.130
Moving the sink or adding a prep sink or pot fillerPlumbing permit (DWV/Water Alteration) with plan reviewSJMC 24.02.100; online DWV/Water Alteration is single-family only
New circuits, an island outlet, under-cabinet lighting or a range hoodElectrical permit; exhaust fan needs a mechanical permitSJPermits online: receptacles, light fixtures, exhaust fan
Gas line to a new range locationPlumbing and mechanical permits (gas rough and final)SJPermits online: Gas Line Rough and Final
Removing or opening a wall, new header or beamBuilding permit with plans (Kitchen Major, structural alteration)Fee schedule processing table; SJMC 24.02.220
Replacing a same-location breaker, or a switch or receptacle in an existing boxNo permitSJMC 24.02.150.6; SJPermits note on replacements

How Much Does a Kitchen Remodel Permit Cost in San Jose?

The Schedule of Fees and Charges effective July 1, 2026 lists two kitchen processing lines, Kitchen Minor at 1.0 hour, $211 and Kitchen Major (structural alteration) at 1.0 hour, $211. The building or combination permit is then charged at $315 per hour of inspection time in tiers of 40, 70, 130 or 250 minutes, with trade work folded into the combination permit or, when filed alone, priced at the greater of a $315 per hour minimum or an itemized amount. Plan check is $325 per hour, 30 minutes minimum over the counter and one hour minimum for a review intake. A minor remodel with a few fixture and circuit changes reviewed over the counter in Tier 2 is about $211 + $367.50 + $162.50, roughly $740. A major remodel that opens a wall and relocates plumbing and gas, in Tier 4 with a one-hour plan check, is about $211 + $1,312.50 + $325, roughly $1,850. The Building Official may adjust the assessment to the real scope, and work started without a permit is charged two times the plan review and inspection cost.

What the City Reviews and Inspects

A remodel that changes systems or structure needs plans drawn to scale showing the existing and proposed layout, the fixtures moved, new circuits and the structural detail for any opened wall; the building official may require an engineer's drawings for a beam. San Jose adopted the 2025 California Residential, Electrical, Mechanical and Plumbing Codes, in effect since January 1, 2026, and the code requires rough plumbing, mechanical, gas and electrical to be inspected before anything is covered and before the framing inspection, then a final inspection when the kitchen is complete. Reinspection fees apply when work is not ready or corrections were not made.

Who Pulls the Permits

A homeowner improving a principal residence occupied for 12 months may pull the permits as owner-builder and do the work or hire licensed trades directly; any contractor must hold a state license for a job of $1,000 or more. The online trade permits are available for single-family and duplex properties without plans, while a structural or relocation scope starts on SJPermits.org and uploads plans to SJePlans. Permits expire after 12 months without a start or 180 days without an inspection showing progress.

How to Get a Kitchen Remodel Permit in San Jose

1

Sort the scope into finish and systems

Finish work is exempt; anything touching plumbing, electrical, gas or walls is permitted work.

2

Pull online trade permits for same-location swaps

Fixture, appliance, receptacle, light fixture, exhaust fan and gas line permits are issued online at SJPermits.org for single-family homes without plans.

3

File plans for relocations or structural work

Start on SJPermits.org and upload to SJePlans: existing and proposed layout, moved fixtures, circuits and any beam detail.

4

Pay processing, permit and plan check

$211 processing (Kitchen Minor or Major), tiered inspection fee at $315 per hour, plan check at $325 per hour.

5

Inspect rough, then final

Rough trades before drywall or cabinets go in, then final; cancel by 2 pm two business days ahead.

Frequently Asked Questions

Not for finish work: SJMC 24.02.120 exempts painting, tiling, cabinets, counter tops and similar work. You need permits once you move or add plumbing, add circuits or lighting, run gas to a new range location, add an exhaust hood, or open or remove a wall.
The FY2026-27 schedule sets a $211 processing fee (Kitchen Minor or Kitchen Major), a building or combination permit at $315 per hour of inspection time in tiers, and plan check at $325 per hour. A minor remodel runs about $740; a structural remodel with relocated plumbing about $1,850.
No. Cabinets and counter tops are named in the city's list of finish work exempt from a building permit, as long as the sink, appliances and circuits stay where they are. Replacing the sink or dishwasher in place is an online fixture or appliance permit.
Yes. SJPermits.org lists Appliance - New or Replacements and Fixture Single Replacement as online permits, and the plumbing exemption covers only leak repair and clearing stoppages, not replacing a fixture. The online permit needs no plans.
No. Relocating a sink rearranges pipes and fixtures, which the plumbing exemption excludes, so it needs a plumbing permit; SJPermits lists DWV / Water Alteration as an online permit for single-family homes. A moved wall or gas line brings building and mechanical permits with it.
The city does not publish a review timeline. Online trade permits issue at checkout; a remodel with plans is reviewed either over the counter or through plan check at $325 per hour, and the permit then stays valid for 12 months to start work and 180 days between inspections.