Permit Required? Depends (systems and structure)
Typical Fee Range $57–$560 Cabinets, counter tops, tile and paint are exempt; piping, wiring, hoods, walls are not.
Fee Method Trade permits $47 + items; building by valuation

What's Required in Albuquerque

  • Cabinets, counter tops, tile, paint and flooring need no building permit (UAC 109.2.1).
  • Any installation or alteration of kitchen piping requires a plumbing permit; same-configuration fixture replacement does not.
  • New wiring, circuits, outlets or fixtures require an electrical permit; like-for-like appliance and receptacle replacement does not.
  • A ducted exhaust hood requires a mechanical permit and must be installed by a licensed contractor.
  • Removing or altering a wall or enlarging the kitchen requires a building permit with plans and 65 percent plan review.
  • Homeowners may hold plumbing or electrical permits only after passing the city's written exam at 75 percent or better.
  • Building permits go to the owner-occupant (one homeowner's permit per 12 months) or a GB-2/GB-98 general contractor; rentals need a licensed contractor.
  • Trade permits expire 180 days after issuance; a rough inspection is needed before covering work.

Do you need a permit to remodel a kitchen in Albuquerque?

Not for the cosmetic layer. The 2024 Uniform Administrative Code (109.2.1) exempts painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work from a building permit, and repairs under $1,000 in valuation. Everything behind the finishes is permitted work, and Albuquerque splits it by trade. The Building Safety permits page lists installation or alteration of bathroom or kitchen piping and installation of an exhaust hood under plumbing/mechanical permits, and any installation, addition, alteration or replacement of wiring, devices or equipment under electrical permits. Removing or altering a wall, or enlarging the room, is a building permit; the FAQ says building permits and inspections are required for residential remodeling work.

Two exemptions save money on smaller jobs. A plumbing permit is not required to replace a fixture with the same type of configuration, or to pull and reset a toilet, so a new sink and faucet in the same spot with no piping changes is permit-free. An electrical permit is not required to replace a fixed listed appliance of the same type and rating in the same location or to swap receptacles for the same type, so a new dishwasher or range on the existing circuit is exempt. Add a circuit, move an outlet, relocate the sink drain or run a new gas line and the permits come back.

How much does a kitchen remodel permit cost in Albuquerque?

Trade permits are per item with a $47 administrative charge on each application. Plumbing: $10 per fixture including drain and vent, $6 per gas outlet. Electrical: $1.50 per outlet, switch or fixture for the first 20, $8 for each residential fixed appliance of 30 amps or over. Mechanical: $14 for a range hood with its duct. A building permit, when a wall or the structure changes, is UAC Table 112-A on the stated valuation of the work, multiplied by the 0.50 modifier for one- and two-family homes, plus 65 percent plan review. Worked examples:

  • Relocating the sink and adding a dishwasher line: $47 + 2 x $10 = $67 plumbing permit. A new gas outlet for the range adds $6.
  • New circuits for a range, microwave and 8 outlets: $47 + $8 + 8 x $1.50 = $67 electrical permit.
  • Ducted range hood: $47 + $14 = $61 mechanical permit.
  • $30,000 remodel removing a wall: Table 112-A gives $391.75 + 5 x $10.10 = $442.25; x 0.50 = $221.13 permit + $143.73 plan review = $364.86, plus the three trade permits above, about $560 in all.
What you are doingCity filingRule
New cabinets, counter tops, backsplash, flooring, paintNo permitUAC 109.2.1 finish-work exemption.
New sink and faucet in the same locationNo permitReplacement of plumbing fixtures with the same type of configuration is exempt.
New range or dishwasher on the existing circuit and hookupsNo permitSame type and rating in the same location is exempt from an electrical permit.
Moving the sink, adding a dishwasher or gas range linePlumbing permit$47 plus $10 per fixture and $6 per gas outlet; licensed plumber or exam-qualified homeowner.
New circuits, outlets or under-cabinet lightingElectrical permit$47 plus $1.50 per outlet or fixture and $8 per 30 amp appliance circuit.
Ducted range hood to the exteriorMechanical permit$47 plus $14 for the hood and its duct; equipment and ductwork only by a licensed contractor.
Removing a wall or opening the kitchen to the next roomBuilding permit + plan review + tradesValuation-based; about $365 at $30,000 before trade permits.

Who pulls the permits?

Trade permits go to New Mexico CID-licensed contractors. A homeowner can hold an electrical or plumbing permit only after passing the city's written exam with a score of 75 percent or greater: four hours per exam, a retake after 30 days, two attempts, one passing exam a year. There is no homeowner mechanical permit; the permits page says equipment and ductwork can only be completed by a licensed contractor. The building permit for structural work can go to the owner-occupant under a homeowner's permit (one per 12 months, notarized affidavit) or to a GB-2 or GB-98 general contractor; rented homes always use a licensed contractor. Plan review takes about two and a half weeks when plans are required; trade permits without plans are issued on application and expire 180 days after issuance. Expect a rough inspection before walls are closed and a final on each permit.

How to Get a Kitchen Remodel Permit in Albuquerque

1

Sort the scope by trade

List what moves: piping (plumbing permit), wiring (electrical permit), hood or ductwork (mechanical permit), walls or structure (building permit). Finish-only work needs nothing.

2

Line up who pulls each permit

Licensed plumbing, electrical and mechanical contractors pull their own permits; a homeowner can pull plumbing or electrical only after passing the city exam.

3

Apply in ABQ-PLAN

For structural work upload a floor plan of the existing and new layout with fixture and appliance locations, state the valuation and pay plan review; trade permits are applied for per item.

4

Rough-in inspections

Call plumbing, electrical and mechanical rough inspections before drywall or cabinets cover the work; framing is inspected after the trades are approved.

5

Finals

Request the final inspection on each permit within 180 days of issuance; re-inspections cost $47 each.

Frequently Asked Questions

No. The city's Uniform Administrative Code exempts cabinets, counter tops, tiling, painting and similar finish work from a building permit. Keep the sink, appliances and outlets where they are and no trade permits are needed either; the moment piping, wiring or a wall changes, the relevant permit applies.
Yes, a plumbing permit. Installation or alteration of kitchen piping is on the city's plumbing permit list, and only same-configuration fixture replacement is exempt. The fee is a $47 administrative charge plus $10 per fixture, so a relocated sink plus a dishwasher line is $67, pulled by a licensed plumber or an exam-qualified homeowner.
From about $57 for a single-fixture plumbing permit to roughly $560 for a $30,000 remodel that removes a wall. Trade permits are $47 plus per-item fees; a building permit is Table 112-A on the valuation times 0.50 plus 65 percent plan review, about $365 at $30,000.
Only if you pass the city's written electrical exam with a score of 75 percent or greater, which takes up to four hours and allows two attempts 30 days apart. Otherwise a licensed electrical contractor pulls the permit. Replacing an appliance or receptacle with the same type in the same location needs no permit at all.
A ducted hood does. Installation of an exhaust hood is on the city's mechanical permit list, and Table 112-C charges $14 for each hood served by mechanical exhaust including its ducts, plus the $47 administrative charge. Equipment and ductwork can only be installed by a licensed contractor.
Trade permits that need no plans are issued on application and are void 180 days after issuance. A building permit for structural changes goes through plan review, which the Building Safety FAQ puts at approximately two and a half weeks for residential projects, with the permit issued once every division approves.