Permit Required? Depends on scope (finishes exempt)
Typical Fee Range $580–$1,220 Tile, counters and paint are exempt; fixture replacement is an online plumbing permit
Fee Method $211 processing + tiered inspection fee + plan check

What's Required in San Jose

  • Tile, paint, cabinets and counter tops are exempt finish work (SJMC 24.02.120.A.9)
  • Removing and reinstalling the same toilet, stopping leaks and clearing stoppages need no plumbing permit; replacing a fixture does (SJMC 24.02.130)
  • Fixture replacements, DWV/water alterations and water heater replacements are online plumbing permits for single-family homes
  • New circuits, receptacles and light fixtures need an electrical permit; same-location switch or receptacle replacement does not
  • An exhaust fan needs a mechanical permit (online)
  • Removing a wall or enlarging the room is a building permit with plans; Bath processing line $211
  • Rough plumbing, mechanical and electrical inspected before concealment; final at completion
  • Permits expire after 12 months without a start or 180 days without progress

Do You Need a Permit to Remodel a Bathroom in San Jose?

For the surfaces, no; for the fixtures and wiring, yes. San Jose Municipal Code 24.02.120 exempts painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work, so retiling the floor, a new vanity cabinet and top, and paint need nothing. The plumbing exemption in 24.02.130 is narrow: stopping leaks, clearing stoppages, and the removal and reinstallation of water closets, provided such repairs do not involve or require the replacement or rearrangement of valves, pipes or fixtures. Put in a new toilet, tub, shower valve or faucet and it is a fixture replacement, which SJPermits.org issues as an online plumbing permit without plans. Moving a drain, converting a tub to a shower, adding a fan or a circuit, or taking out a wall goes further and needs a permit with review.

San Jose Bathroom Remodel Rules by Scenario

What you are doingCity filingRule
New tile, paint, vanity cabinet and top, mirror; same fixturesNo permitSJMC 24.02.120.A.9
Pulling and resetting the same toilet, fixing a leak or clearing a drainNo permitSJMC 24.02.130.B
New toilet, faucet, shower valve or tub in the same locationOnline plumbing permit (Fixture Single Replacement; multiple fixtures also online)SJPermits online permits
Moving a drain, tub-to-shower conversion, or adding a fixturePlumbing permit with review (DWV / Water Alteration)SJMC 24.02.130.A; 24.02.100
New exhaust fan, or a new circuit, outlet or lightMechanical permit for the fan; electrical permit for wiringSJPermits online: Exhaust Fan, Receptacles, Light Fixtures
Water heater replacementOnline plumbing permit; $52 processing at the Permit CenterSJPermits; fee schedule processing table
Removing a wall or enlarging the bathroomBuilding permit with plans (Bath line, $211 processing)Fee schedule processing table; SJMC 24.02.220

How Much Does a Bathroom Remodel Permit Cost in San Jose?

The Schedule of Fees and Charges effective July 1, 2026 lists a Bath permit processing line at 1.0 hour, $211. The building or combination permit is charged at $315 per hour of inspection time in tiers of 40, 70, 130 or 250 minutes, and plan check runs $325 per hour with a 30-minute over-the-counter minimum. A same-footprint remodel with new fixtures, a fan and a circuit in Tier 1 is about $211 + $210 + $162.50, roughly $585. A remodel that moves the drain and takes out a wall, in Tier 3 with a one-hour plan check, is about $211 + $682.50 + $325, roughly $1,220. Trade permits filed on their own are the greater of a $315 per hour minimum or an itemized amount; a water heater swap carries only a $52 processing charge at the Permit Center. The Building Official may adjust the assessment to the actual scope, and unpermitted work is charged two times the plan review and inspection cost when it is found.

What Gets Inspected

The code requires rough plumbing, mechanical and electrical to be inspected before they are covered and before the framing inspection, so the new drain, vent, supply lines, fan duct and wiring are checked with the walls open, and a final inspection closes the permit. San Jose applies the 2025 California Residential, Plumbing, Mechanical and Electrical Codes, in effect since January 1, 2026. Reinspection fees can be charged when the work is not ready or corrections are not made, and the permit expires after 12 months without a start or 180 days without an inspection showing progress.

Who Pulls the Permits

You can, as owner-builder, if you are improving a principal residence you have lived in for 12 months, or you can hire licensed trades directly; any contractor needs a state license for a job of $1,000 or more. Online permits are available around the clock at SJPermits.org for single-family and duplex properties; a relocation or structural scope starts there and uploads plans to SJePlans. Inspections are scheduled online and must be cancelled by 2 pm two business days ahead to avoid a charge.

How to Get a Bathroom Remodel Permit in San Jose

1

Split the scope

Surfaces are exempt; fixtures, wiring, fans and walls are permitted work.

2

Pull online permits for in-place replacements

Fixture Single Replacement, Exhaust Fan, Receptacles and Light Fixtures are issued at SJPermits.org without plans.

3

File plans when plumbing moves or walls change

Start on SJPermits.org and upload to SJePlans: existing and proposed fixture layout, drain and vent changes, any structural detail.

4

Pay the fees

$211 Bath processing, tiered inspection fee at $315 per hour, plan check at $325 per hour; standalone trade permits carry a $315 minimum.

5

Inspect rough and final

Call rough inspection before drywall or tile backer goes on; cancel by 2 pm two business days ahead.

Frequently Asked Questions

Not for tile, paint, a vanity cabinet or counter top, which SJMC 24.02.120 lists as exempt finish work. Replacing a toilet, tub or faucet is an online plumbing permit; moving plumbing, adding a fan or circuit, or removing a wall needs a permit with review.
About $585 for a same-layout remodel and about $1,220 when plumbing moves or a wall comes out, built from the published pieces: $211 Bath processing, a building or combination permit at $315 per hour of inspection time in tiers, and plan check at $325 per hour.
Yes if it is a new toilet. The plumbing exemption covers only removing and reinstalling the same water closet without replacing or rearranging valves, pipes or fixtures. SJPermits.org issues a Fixture Single Replacement plumbing permit online with no plans.
Yes. Rearranging pipes or fixtures is outside the exemption, so a moved drain, a tub-to-shower conversion or an added fixture needs a plumbing permit, and rough plumbing must be inspected before it is covered.
Yes. Exhaust Fan is listed as an online mechanical permit at SJPermits.org for single-family, multifamily and commercial properties, and any new circuit for it needs an electrical permit. Replacing a switch or receptacle in an existing location needs no permit.
Yes. California's owner-builder exemption covers a homeowner improving a principal residence occupied for 12 months, doing the work personally or hiring licensed subcontractors. Contractors need a state license for any job of $1,000 or more.