Permit Required? Required (plan review)
Typical Fee Range $2,600–$5,250 Plus electrical, King County plumbing, side sewer and the county sewer capacity charge
Fee Method Table D-1 index on value: 100% permit + 100% plan review

What's Required in Seattle

  • Every AADU or DADU needs an SDCI construction addition/alteration permit with plan review; legalizing an existing unit needs a permit to establish use.
  • Permit and plan review fees are each 100 percent of the Table D-1 index on the valuation-table value ($186.29 per sq ft for Type VB R-3 construction), plus 5 percent technology fee and the $6.50 state surcharge; about 75 percent is due at intake.
  • The unit must meet current Seattle residential, building, mechanical, electrical, energy, land use, ECA and shoreline codes; a DADU is not treated as an accessory structure under the building codes.
  • DADU limits in NR zones (Tip 116B): 3,200 sq ft minimum lot, 1,000 sq ft maximum unit, 40 percent of the required rear yard, 5 ft setbacks (0 ft on an alley), no shoreline districts.
  • No parking is required for an ADU, but existing required parking cannot be removed without replacement.
  • Separate SDCI electrical permit (contractor applies unless the owner does all the work) and Public Health plumbing permit ($137 plus $27 per fixture); a side sewer permit may be required.
  • Sign the King County sewer capacity charge acknowledgment; the county bills quarterly for 15 years after the connection.
  • Pre-approved standard plans are eligible only in NR zones with no ECA and under 750 sq ft of ground disturbance.

Do You Need a Permit for an ADU in Seattle?

Yes, always, with full plan review. SDCI's ADU page says a unit is not legal unless established through a permit: adding a unit inside the house (an AADU) or building a backyard cottage (a DADU) takes a construction addition/alteration permit, and legalizing an existing unit takes a permit to establish use. Tip 101 confirms plan review for every AADU and DADU. The fee is value-based; SDCI's own 2026 example is a 500 sq ft DADU valued at $93,145 paying $3,453 in plan review and permit fees, up 18.7 percent from 2025. Seattle allows two ADUs per lot with a principal unit, including two DADUs, with no parking requirement. Pre-approved DADU plans get a permit in 2 to 6 weeks in most cases.

Seattle ADU Permit Rules by Scenario

What you are doingCity filingRule
New detached ADU (backyard cottage), 500 sq ftAddition/alteration permit with plan review: $3,453 (SDCI example) plus 5 percent and $6.50SDCI 2026 Fee Summary; ADU page
DADU built from a pre-approved standard plan in an NR zone, no ECA, under 750 sq ft of ground disturbanceSame permit on the expedited track, 2-6 weeks in most casesSDCI ADU page; Portal help article
AADU inside the existing house (basement or upper-floor conversion)Addition/alteration permit with plan review, value-basedSDCI ADU page; Tip 116A
Legalizing a unit that already exists without a permitConstruction permit to establish useSDCI ADU page
Wiring the unit (new feeder, subpanel, circuits)SDCI electrical permit; contractor applies unless the owner does all the workTip 116B; Table D-15
Plumbing for kitchen and bathPublic Health plumbing permit: $137 plus $27 per fixtureTip 116B; PHSKC fee schedule
Connecting to the sewerKing County capacity charge billed quarterly for 15 years; side sewer permit may be requiredTip 116B; ADU page

How Much Does an ADU Permit Cost in Seattle?

SDCI prices the construction permit from Table D-1 of the 2026 Fee Subtitle on value, set from its building valuation data: Director's Rule 5-2025 values one- and two-family residential construction (Group R-3) at $186.29 per square foot for Type VB wood frame. Permit fee and plan review fee are each 100 percent of the Development Fee Index, plus a 5 percent technology fee and the $6.50 state surcharge; about 75 percent is due at intake.

SDCI's own example: 500 sq ft x $186.29 = $93,145. Table D-1 gives $1,471.50 for the first $75,000 plus $1.40 per $100 above it (182 x $1.40 = $254.80), an index of $1,726.30; doubled for permit plus plan review that is $3,452.60, which SDCI rounds to $3,453; with technology fee and state surcharge, $3,631.73. A 1,000 sq ft DADU, the NR-zone maximum, is $186,290 of value: $2,402.75 for the first $175,000 plus 12 x $7.75 = $93, index $2,495.75, doubled $4,991.50, all in $5,247.58. An AADU conversion valued at $60,000 (labor and materials) has an index of $1,246.50 and totals $2,624.15. Then budget the SDCI electrical permit (a 60 to 200 amp feeder is $146 plus $26.28 per small circuit and $55.48 administration), the Public Health plumbing permit ($137 plus $27 per fixture, about $326 for seven), a possible side sewer permit, and the King County capacity charge, billed quarterly for 15 years.

Size, Height and Placement Rules

Tip 116B (2023) sets the DADU limits in Neighborhood Residential zones: a lot of at least 3,200 sq ft, a unit of no more than 1,000 sq ft gross (excluding garages, exterior-access storage, small porches and below-grade area), accessory structures covering no more than 40 percent of the required rear yard, and no parking requirement, though existing required parking cannot simply be removed. Tip 116A caps an AADU at 1,000 sq ft unless that part of the house existed on December 31, 2017. SDCI's 2025 zoning summary lists ADU setbacks of 5 ft (0 ft on an alley) and a 32 ft zone height limit. DADUs are barred in shoreline districts. Ordinance 127376 rewrote SMC 23.44 in 2025 and the ADU standards now sit in SMC 23.42.022, so confirm the Tip figures with SDCI's free land use coaching. Owner occupancy is not among either Tip's criteria, and SDCI publishes a form releasing older owner-occupancy covenants.

The Process

File a Building & Land Use Pre-Application in the Seattle Services Portal with a site plan; SDCI assigns a record number and may require a pre-application site visit. Intake appointments can be 2 to 4 months out, so upload the full plan set (site plan, floor plans of both units, elevations, structural plans, energy calculations, capacity charge form) early to be pulled forward. After intake you pay the fees and respond to corrections; a tenant may occupy the unit only after the final inspection.

How to Get a ADU Permit in Seattle

1

Check feasibility

Use the ADUniverse search tool and SDCI's GIS map to confirm the zone, lot size, ECA status and shoreline overlay, then decide between a custom design and a pre-approved DADU plan.

2

Submit the pre-application

File a Building and Land Use Pre-Application in the Seattle Services Portal with a site plan and legal description; SDCI assigns a record number and may schedule a pre-application site visit.

3

Prepare the full plan set

Site plan, floor plans of both units, elevations, structural plans, energy calculations, the Statement of Financial Responsibility and the King County capacity charge form; upload everything early to move your intake appointment up.

4

Pay fees and clear corrections

About 75 percent of the value-based fee is due at intake; respond to correction letters in the portal until the plans are approved and the permit is issued electronically.

5

Build, inspect, then occupy

Pull the electrical permit and the Public Health plumbing permit, schedule inspections through the portal or (206) 684-8900, and rent the unit only after the final inspection is approved.

Frequently Asked Questions

SDCI's 2026 fee summary prices a 500 sq ft DADU (valued at $93,145) at $3,453 in permit and plan review fees, about $3,630 with the 5 percent technology fee and state surcharge. A 1,000 sq ft DADU runs about $5,250 and a $60,000 AADU conversion about $2,620. Electrical, Public Health plumbing, side sewer and the King County capacity charge are extra.
Yes. SDCI's ADU page says only two of a lot's units may be ADUs, and the code update implementing state HB 1337 allows two ADUs per lot with a principal unit, including the option of two detached units. ADUs count toward density, floor area and lot coverage but are exempt from parking, street improvement and mandatory housing affordability requirements.
Tip 116B limits a DADU in Neighborhood Residential zones to 1,000 gross square feet, excluding garage area, exterior-access storage, porches and covered decks under 25 sq ft, and below-grade floor area, on a lot of at least 3,200 sq ft. The zone height limit is 32 ft plus pitched-roof allowances. Confirm current figures with SDCI, since the ADU standards moved to SMC 23.42.022 in 2025.
SDCI says a DADU built from a pre-approved standard plan gets its permit in 2-6 weeks in most cases. A custom ADU goes through full plan review: Tip 116B warns the intake appointment alone may be 2-4 months out, though uploading a complete set early can move it up, and correction rounds follow. Electrical and plumbing permits run separately.
Neither Tip 116A nor Tip 116B lists owner occupancy among the criteria for establishing an ADU, and SDCI publishes a Release of Owner Occupancy Covenant form for ADUs permitted under older rules. Tip 116B does say the unit may not be subdivided from the main house. Ask SDCI to confirm the current text of SMC 23.42.022 before relying on this.
A sewer connection charge King County levies on structures with new connections, separate from the monthly sewer bill. SDCI reports every ADU permit to the county, you sign an acknowledgment form during the application, and the bill arrives about three months after the connection, payable quarterly for 15 years or in a discounted lump sum. The amount is set by King County, not SDCI.